PT Supreme Energy Muara Laboh

Geothermal development activities are a series of activities that includes drilling of production wells and injection wells, construction of field facilities, including power plants and steam above ground system, which are used for electricity production operations from geothermal resources. In t...

PT Supreme Energy Rantau Dedap

SERD started its civil construction in early January 2013 and completed ± 42 km of its access road. In 2015 SERD has completed 6 explorations drilling wells: RD-B1, RD-B2, RD-C1, RD-I1, RD-I2, RD-C2, and in 2016 completed the Feasibility Study confirming 92 MW (gross) proven reserve capacity. Aft...

PT Supreme Energy Rajabasa

In 2014, SERB focused on engineering design related to Jetty construction, piping systems, sea water facilities, pumping facilities, and facilities for the supply of electricity generators. SERB has proactively conducted social and legal approach in order to improve situation and condition in the...